Lake County is rebuilding and expanding the Clearlake clinic where it treats people for mental illness and addiction. When crews pulled up the floor, they found a crack running the full length of the building.
The fix would cost $842,878 and add 120 working days to the job, according to a change order, the paperwork to change the construction contract, on the Board of Supervisors’ agenda for Tuesday, Nov. 17. That would raise the contract with Cupples & Sons Construction from $4,465,409 to $5,308,287, an increase of about 19%.
What the crews found
The crack runs “the full length of the building from East to West,” says the memo from Interim Public Works Director Stephen Carter and Behavioral Health Director Elise Jones. Working with the contractor, engineers found that “expansive soil,” ground with clay in it that swells when wet and shrinks when dry, had let the edges of the building sink as much as 1.75 inches in places. That knocked parts of the building out of line and broke the concrete floor inside.
The plan is to tear out the old 4-inch floor and pour a new slab of steel-reinforced concrete 12 inches thick, tied into the existing foundation around the edges. The contractor’s cost sheet also covers tearing down and rebuilding walls that were supposed to stay, along with the wiring, drywall, insulation and doors in them.
The memo calls the crack “unforeseen field conditions.” When the county was getting ready to apply for state money for the project in October 2024, its memo said the work “will add 16 office spaces and remediate significant structural issues.” Neither document says whether those issues and the crack are the same problem.
Who the clinic serves
The clinic sits at 7000-B South Center Drive. The county’s addiction services page lists Clearlake and Lucerne as the two towns where it provides services itself.
The expansion is paid for with a $7,728,800 state grant, plus county matching money. The grant comes from the Behavioral Health Infrastructure Bond Act of 2024, the state bond known as Proposition 1. Lake County’s grant agreement promises 22 offices, two group rooms and 355 new treatment slots a year: 242 for mental healthcare and 113 for addiction treatment. It names youth, people in the justice system, Medi-Cal patients and homeless residents as the people it means to reach.
A 2025 county memo adds rooms for same-day visits, for follow-up care after a crisis, and for medication treatment for addiction, including long-acting shots.
3 finish dates
The project description in the grant agreement, which supervisors approved in October 2025, projects completion in the last three months of 2026. A state list of grant winners says spring 2027. Tuesday’s memo says the job is about 20% done and on schedule to be substantially finished in September 2027, even with this change.
Supervisors awarded the contract on July 28 as part of the consent calendar, a group of routine items passed in one vote. Cupples was the low bidder of six. The original contract gave the company 240 working days. The change would raise that to 360.
The contractor’s cost sheet lists the schedule impact as 150 days in one box and 120 days in another. The county’s change order uses 120.
Who pays
The county “anticipates funding Change Order No. 1 within existing project resources,” Tuesday’s memo says. The grant agreement makes the county responsible for any cost above the state’s $7.7 million. It also requires the county to tell the state’s grant administrator before making a change that costs more than $100,000 or pushes back the finish date. Tuesday’s memo doesn’t say whether that has happened.
Nor does it say where clinic clients are being seen while crews work. The county’s web page still lists the clinic’s address and phone number, 707-994-7090.
Supervisors meet at 9 a.m. Tuesday at 255 N. Forbes St. in Lakeport. The change order is item 7.3 and has no set time.