The Vacation Beach summer dam has not been installed since it failed on Aug. 29, 2024. This page tracks its status.
Current status
As of Oct. 11, 2026: out for a third straight summer, no installation date. The Russian River Recreation and Park District is hiring a project manager for a repair that now covers uprights 5 through 0 and could extend to replacing uprights 4, 3, 2 and 1. Its board minutes say the project “has grown beyond what can reasonably be managed entirely in-house.”
Timeline
- Aug. 29, 2024 — Dam breaches; a steel stringer on the Neeley Road side fails.
- Nov. 5, 2024 — State report bars reinstallation until repair plans and completed work are both approved.
- 2025 — No dam, no crossing. District hires structural and geotechnical engineers; state requires a streambed alteration agreement.
- May 12, 2026 — District announces final state signatures received.
- May 21, 2026 — State re-inspection finds new damage outside the approved scope.
- June 11, 2026 — District says repairs must be re-scoped and re-permitted; no installation date.
- July 15, 2026 — Board told an annual inspection found concerns beyond the repair; earlier efforts to find a project manager had failed.
- Aug. 12, 2026 — Board votes 4-0 to approve a request for proposals for a project manager.
- Sept. 4, 2026 — District issues the request; proposals due Sept. 21, board award targeted for Oct. 5.
- Sept. 27, 2026 — Neighbors start a change.org petition for the repair.
Full story: Vacation Beach dam repair outgrows park district’s staff.
Dam questions go to the Russian River Recreation and Park District, 707-869-9184. Crossing questions go to Sonoma Public Infrastructure, 707-565-3040. Johnson’s Beach in Guerneville has its own separate dam.