Lakeport families who need a two- or three-bedroom apartment they can afford can now apply for Parkside Apartments, a 64-unit complex at 1310 Craig Ave.
A notice on the city of Lakeport’s website, online since at least mid-October, says the complex is leasing. Danco Property Management, which will run the complex, takes applications at 707-362-7889 and through an online form on its website.
Sixty-three of the 64 units carry rent limits. The last one is for the on-site manager. Half the units have two bedrooms and half have three, according to the state tax credit staff report from December 2024. The rent limits last 55 years.
Who can rent here
Each rent-limited unit is set aside for a household at a set share of the area’s median income. The 2024 state report lists 15 units for households at 30% of median, eight at 40%, 14 at 50% and 26 at 60%.
In Lake County, 60% of median works out to $58,260 a year for a family of four and $46,620 for a couple, under the state’s 2026 income limits. At 30%, the limits are $29,130 for four people and $23,310 for two.
Each income level has its own rent. The 2024 filings listed proposed rents from $594 a month for a two-bedroom at the 30% level to $1,312 for a three-bedroom at the 60% level. Those figures include a $12 utility allowance. The state updates its maximum rents for each level every year. Danco’s project page doesn’t list current rents.
The application asks for three years of housing history. It says the company accepts service and emotional support animals only.
The complex has five two-story buildings, a pool, a fitness room, a community building with a kitchen, a laundry room and a play area, according to Danco’s project page.
When it opens
Neither the city’s notice nor Danco’s project page gives a move-in date. The 2024 state report expected construction to finish in December 2026. The city’s July 2025 announcement said January 2027.
Crews had finished the underground work and were starting on the buildings in early February, Community Development Director Joey Hejnowicz told the council, according to the Feb. 3 minutes. The city’s 2026-27 budget document, on the council’s June 30 agenda, listed the complex as 50% complete.
What it cost
The state report put the cost at $36.3 million when Danco applied. Federal tax credits and tax-exempt bonds pay for most of it. Federal block grants passed through the city and state housing grants cover much of the rest.
In August, city staff told the council the project faced a $1,978,000 gap “due to changes in tax credit pricing, higher debt costs, and increased construction-related expenses,” according to the Aug. 18 staff report.
“Without the additional $1,978,000 allocation, the Parkside Apartments project faces a significant risk of delay or potential restructuring,” the report says.
The council voted 3-0 to accept $1,978,000 more in federal disaster-recovery money from the state housing department, the minutes show. Council Member Kim Costa was absent. Council Member Price stepped out because she is the real estate agent for three nearby properties on Fenway Avenue.
Neighbors’ worries
The apartments are the first phase of a larger development the city lists at 176 homes. The council approved the project 3-1 in November 2022 over objections from people living next to the site, with Michael Froio opposed, Lake County News reported in 2024. Neighbors raised safety and traffic concerns, and Froio, who was mayor in 2024, wanted a second way in, the paper reported. As designed, it said, the complex would be reached only by Charlie Jolin Way, the main road into Westside Community Park.
A September 2024 city staff report says the developer planned a bridge over Forbes Creek for emergency vehicles only, linking Wrigley Street and Craig Avenue, with gates or bollards to keep other cars off. At that same meeting, a Danco representative, Chris Westlake, said the developer wanted to build a full-access bridge, Lake County News reported. City records since then, including the August staff report, call it an emergency vehicle access bridge. In April, city staff reported that they had approved the bridge design. Council agendas and minutes posted since then don’t say whether it has been built.
Costa raised neighbors’ complaints in September. She told the council about cleanup needs near the site and reports of reckless driving, the minutes show.